Sampson’s Island Dredge & Dead Neck Nourishment

Cotuit Dredge Milestones:

 

  • September 10, 2020DEAD NECK SAMPSON’S ISLAND DREDGING & BEACH NOURISHMENT PROJECT – PHASE 3  The Town of Barnstable, working with Barnstable County Dredge, will be starting Phase 3 of the Dead Neck Sampson’s Island Dredging & Beach Nourishment project on Monday, September 14th.  The project includes dredging of approximately 40,000 cubic yards of sand on the west end of the island, which will be re-used onsite for habitat and beach nourishment.  Vessels for the transport of Barnstable County Dredge and general contractor employees will be anchored at the Cotuit Town dock for the duration of construction. Dredging operations are anticipated to begin on September 21, 2020 and anticipated to last through November 20, 2020, with beach nourishment activities anticipated to last through December 30, 2020.  Weather pending, construction/dredging will be on-going, Monday through Saturday from 7:00 AM to 5:00 PM until completion of this phase of the project. Boat operators in Cotuit Bay and the Seapuit River are encouraged to use caution when operating in this area during dredging and nourishment operations.
  • August 7, 2020  View Final Phase 3 Bid Invitation Documents and Information HERE
  • June 8, 2020    Town awarded $500,000 Grant from the 2020 Round of the Massachusetts Dredging Program from Executive Office of Housing and Economic Development for Phase 3
  • January, 2, 2020 View Process HERE
  • December 20, 2019 Phase 2 Completed ahead of schedule
  • September 26, 2019 Successful Bidder Awarded Phase 2 – Dig It Construction, $375,000
  • PHASE 2 OF DREDGING OF COTUIT BAY ENTRANCE CHANNEL AND WESTERN TIP OF SAMPSON’S ISLANDThe Department of Public Works, in collaboration with Barnstable Clean Water Coalition, Massachusetts Audubon Society, and Barnstable County, will begin operations for Phase 2 of the dredging of the Cotuit Bay Entrance Channel and the western tip of Sampson’s Island during the week of October 15, 2019.  Dredging is anticipated to commence on or about October 30th.   This work is a continuation of the work completed last year and will widen the existing channel by approximately an additional 130 feet.  The dredged material will be utilized for beach nourishment purposes on the southern side of the eastern end of the island and for a habitat enhancement area. Weather pending, dredging operations will be on-going, Monday through Saturday from 7 AM to 5 PM until completion of this phase of the project.  Dredging operations will be completed by January 14, 2020.
  • February 1, 2019: Nourishment cleanup/Demobilization complete
  • January 22, 2019: View Barnstable County Sand Drifter Dredge HERE
  • January 15, 2019: Close of Permitted Dredge Window
  • Week of November 5, 2018: Dredging Operations commence.  This phase of the project will widen the existing channel by approximately 130’ and the dredged material will be utilized for beach nourishment purposes on the southern side of the eastern end of the island (Dead Neck Beach) and for a habitat enhancement area. Weather permitting, dredging operations will be on-going, Monday – Saturday from 7 AM to 5 PM until completion of this phase of the project.  Dredging operations will be completed by January 15, 2019. 
  • November 25, 2018: View Aerial Drone footage  HERE
  • Week of October 22, 2018: Dredging operations commence
    • Anticipate ±50 working days of dredging
    • County dredge operates 6 days a week, 10 hours per day
  • October 16, 2018: Beginning of Permitted Dredge Window
  • Permit Public Comment Period 10/26-11/26/15 
  • Week of October 15, 2018:
    • County Dredge mobilization
    • Contractor mobilization
    • Contractor strips vegetation and builds dewatering pits
  • October 11, 2018: Anticipated bid close date
  • September 24, 2018: Notify Misc. Agencies of Project Start
  • September 20, 2018: Anticipated date to issue Invitation for Bid for dewatering/beach  nourishment contractor
  • Week of September 10, 2018: Natural Resources to conduct shellfish survey
  • Update: August 25, 2018: The State awarded $3.6 million in grants to support ten dredging projects along the state’s coastline last week. The grants, awarded through 2018 Navigational Dredging Pilot Program, are expected to remove roughly 188,000 cubic yards of sediment from the harbors of eleven different communities.Barnstable has been granted $1,000,000 to remove 44,000 cubic yards of sediment and coastal dune from the Cotuit Bay channel, increasing its width by 50-percent. The 2018 pilot program awards communities funding on a competitive basis, emphasizing on shovel-ready projects that already have secured permits from the local, state, and federal levels. The program also requires a 50-percent match commitment from municipalities receiving the funding.Update: July 26, 2018: In the Matter of Three Bays Preservation, Inc. and Massachusetts Audubon Society, Docket No. 2017-020 The Massachusetts Department of Environmental Protection (DEP) Presiding Officer has ruled in favor of Three Bays Preservation, Inc. in an 84-page ruling. DEP Commissioner Suuberg now has 30 days to adopt and certify this decision. Contact Barnstable Clean Water Coalition HERE to see a copy of this Recommended Final Decision. Counsel advises that once certified, phase 1 dredging could begin on October 15th as the permits allow. Among the many benefits of this restoration project, water quality, in Cotuit Bay, is expected to improve by three to seven percent. Great for people and birds! To date this permitting process has taken over six years at a cost of over one million dollars.

 The Barnstable Clean Water Coalition 


Sampsons

SampsonsHistorical

Audubon

Dead Neck Sampsons Island Dredging/Renourishment Project

VIEW  HERE

News HERE

Tropical Storm Warning


Tropical Storm Warning is in effect for our area

…TROPICAL STORM WARNING REMAINS IN EFFECT…

* LOCATIONS AFFECTED

– Chatham

– Falmouth

– Provincetown

* WIND

– LATEST LOCAL FORECAST: Below tropical storm force wind

– Peak Wind Forecast: 20-30 mph with gusts to 45 mph

– THREAT TO LIFE AND PROPERTY THAT INCLUDES TYPICAL FORECAST
UNCERTAINTY IN TRACK, SIZE AND INTENSITY: Potential for wind 39
to 57 mph

– The wind threat has remained nearly steady from the
previous assessment.

– PLAN: Plan for hazardous wind of equivalent tropical storm
force.

– PREPARE: Remaining efforts to protect property should be
completed as soon as possible. Prepare for limited wind
damage.

– ACT: Move to safe shelter before the wind becomes hazardous.

– POTENTIAL IMPACTS: Limited

 


 

2020 PARKING PERMITS – BEACH STICKERS

Beach chairs

2020 TOWN OF BARNSTABLE

PARKING PERMITS- A.K.A. BEACH STICKERS

Required Year Round 

Beginning May 26, 2020 Stickers will be available online HERE

            Beach Stickers Available through Mail – Information HERE

Lifeguards, bathhouses and gate attendants will begin on June 27, 2020.

Reopening Massachusetts Phase 2

 

Phase 2 has been divided into two parts. Beginning today, Monday, June 8, the following can reopen under certain restrictions:

  • Childcare facilities and day camps
  • Driving and flight school
  • Funeral homes, with occupancy limits
  • Higher education classes including post-secondary, vocational tech and occupation schools may allow students complete required courses for graduation.
  • Historical spaces may reopen outdoor facilities. No guided tours allowed nor can they host functions or gatherings.
  • Hotels and other lodgings, though they may not host events, functions or meetings
  • Outdoor recreation including pools, playgrounds and driving ranges
  • Personal services, such as home cleaning, window washing, education tutoring and career coaching, with social distancing mandated
  • Restaurants, offering only outdoor dining and takeout
  • Retail, with occupancy limits
  • Sports: Professional teams may continue practices starting Monday, though no games or public admission is allowed. Youth sports and adult amateur leagues may resume as well.
  • Warehouses and distribution centers

Beach & Transfer Stickers Available Online

Online Sales: Transfer Station Stickers and Beach Parking Permits starting May 26, 2020

In an effort to assist our community during the COVID-19 emergency, the Town of Barnstable is proud to offer online purchases for transfer station stickers and beach parking permits

In addition to accepting mail-in applications, Barnstable residents can now conveniently go HERE select “Barnstable, MA” in the drop down menu, identify the permit you wish to apply for and download all necessary documents. All online permit sales will be mailed and please allow up to 2 weeks for processing and mailing.

For more information about the Transfer Station Stickers, please visit www.town.barnstable.ma.us/Departments/solidwaste or contact staff at 508-420-2258. For more information about Beach Parking Permits, please visit www.townofbarnstable.us/Departments/Recreation  or contact staff at 508-790-6345.

HIGH WIND WARNING April 13, 2020

…HIGH WIND WARNING IN EFFECT FROM 3:30 PM TO 10 PM EDT MONDAY…

* WHAT…South winds 25 to 35 mph with gusts up to 60 mph
expected.

* WHERE…Barnstable MA, Dukes MA and Nantucket MA Counties.

* WHEN…From 4 PM to 10 PM EDT Monday.

* IMPACTS…Damaging winds will blow down trees and power lines.
Widespread power outages are expected. Travel will be
difficult, especially for high profile vehicles.